Due to the planned upgrade of the SG1 data center infrastructure (Telstra SG2 Paya Lebar), our servers will be relocated to a different server room on Monday, 4th October. Maintenance window scheduled between 15:00-18:00 local time (07:00-10:00 UTC), but reasonable changes in the time of work are possible. During the maintenance, the services located in the SG1.SIN data center will not be available. Please keep this in mind when scheduling your tasks for the specified time. We apologize for any inconvenience this may cause. We encourage users who have additional questions about this post to contact our support team.

Published
Last modified

Event history

Updates and status changes in chronological order. UTC and your local time are shown together.

  1. Published

    Due to the planned upgrade of the SG1 data center infrastructure (Telstra SG2 Paya Lebar), our servers will be relocated to a different server room on Monday, 4th October. Maintenance window scheduled between 15:00-18:00 local time (07:00-10:00 UTC), but reasonable changes in the time of work are possible. During the maintenance, the services located in the SG1.SIN data center will not be available. Please keep this in mind when scheduling your tasks for the specified time. We apologize for any inconvenience this may cause. We encourage users who have additional questions about this post to contact our support team.

  2. Update

    Maintenance window extended for additional two hours due to additional procedures.

    Exact time unavailable in the original archive
  3. Update · Completed

    Migration was successfully completed Oct 04 14:00UTC, IP connectivity was restored immediately after server migration. No further maintenance with this case if required for now.