← Back to Status Page
MaintenanceArchived

Network and Power Maintenance - US4.ORD

Chicago IL · US4.ORD

We will perform scheduled network and power infrastructure maintenance at our US4.ORD location in Chicago from August 3, 2026, at 09:00 CDT through August 4, 2026, at 17:00 CDT (August 3, 14:00 UTC – August 4, 22:00 UTC). The work includes upgrading our routing infrastructure with next-generation hardware and replacing damaged or insufficient-capacity power distribution components. VDS and Dedicated Server customers should expect a brief interruption in network connectivity during the router replacement. The interruption is expected to last approximately 10 minutes, although it may take slightly longer. Some Dedicated Servers may also reboot while power connections are being transferred, as both power feeds require brief maintenance in certain racks. The maintenance is required to improve the capacity and reliability of the network and power infrastructure. If you have any questions, please contact our support team through the customer portal. Any changes or updates related to this maintenance will be published on our status page.

Published
Last modified

Event history

Updates and status changes in chronological order. UTC and your local time are shown together.

  1. Published

    We will perform scheduled network and power infrastructure maintenance at our US4.ORD location in Chicago from August 3, 2026, at 09:00 CDT through August 4, 2026, at 17:00 CDT (August 3, 14:00 UTC – August 4, 22:00 UTC). The work includes upgrading our routing infrastructure with next-generation hardware and replacing damaged or insufficient-capacity power distribution components. VDS and Dedicated Server customers should expect a brief interruption in network connectivity during the router replacement. The interruption is expected to last approximately 10 minutes, although it may take slightly longer. Some Dedicated Servers may also reboot while power connections are being transferred, as both power feeds require brief maintenance in certain racks. The maintenance is required to improve the capacity and reliability of the network and power infrastructure. If you have any questions, please contact our support team through the customer portal. Any changes or updates related to this maintenance will be published on our status page.

  2. Update

    Our team is working on the site, we expect all procedures to be completed within the maintenance window. We will provide further updates if there are any changes other than those previously stated.

    Exact time unavailable in the original archive
  3. Update

    The first part of the work is complete - network traffic has been switched to the new components.